Complete construction of Khimti-Bahrabise transmission line on time: NEA

The Nepal Weekly
March 28, 2023

Nepal Electricity Authority has urged the contractors to complete the construction of the New Khimti-Bahrabise section under the Tamakoshi-Kathmandu 220/400 kV transmission line project in time.

The  NEA has given high priority to the construction of the New Khimti-Bahrabise section to prevent wastage of power of 102 MW Middle Bhotekoshi Hydropower Project under construction at  Sindhupalchowk under the leadership of Chimile Hydropower Project due to lack of connection.

The construction of 400 kV substation in New Khimti and connection work of additional power transformer of 220/132/33 kV, 200 AVA capacity of the substation to increase the capacity of the substation are going on smoothly, according to the NEA. The length of the transmission line from New Khimti substation located at Sankhe in Manthali Municipality-13 of Ramechhap to Bahrabise substation of Sindhupalchowk is 43 km.

Out of the 118 towers of the New Khimti-Bahrabise transmission line section passing through Ramechhap, Dolakha and Sindhupalchowk districts, the foundations of 93 towers have been laid and 73 towers have been installed. The process of land acquisition for the construction of three towers in Ramechhap has been started, according to the NEA. A high-level team, including Managing Director of the NEA Kul Man Ghising, Deputy Executive Director of Broadcasting Directorate Dirghayu Kumar Shrestha, and Deputy Executive Director of Project Management Directorate Tara Prasad Pradhan visited the site on Saturday and discussed the progress of transmission line and substation construction.